Current Project Gallery >Span Tower 20

FIXING OF DOOR FRAMES (09.06.2022)

1st COAT PAINTING WORKS (21.01.2022)

BATHROOM WATER PROOFING WORKS (15.11.2021)

APPLIYING THE WALL PUTTY FOR 3rd FLOOR UNITS (15.10.2021)

APPLIYING THE WALL PUTTY (17.08.2021)

3rd FLOOR UNIT PARTITION WORKS (17.05.2021)

2nd FLOOR UNIT PARTITION WORKS (03.04.2021)

BLOCK 02 – 4th FLOOR SLAB REINFORCEMENT WORKS & 2nd FLOOR UNIT PARTITION WORKS (12.02.2021)

BLOCK 03 – 3rd FLOOR SLAB REINFORCEMENT WORKS (15.01.2021)

BLOCK 01 – 4th FLOOR SLAB CONCRETE WORKS (05.12.2020)

BLOCK 01 – 4th FLOOR SLAB REINFORCEMENT WORKS (25.11.2020)

BLOCK 02 – 3rd FLOOR SLAB REINFORCEMENT WORK (14.10.2020)

BLOCK 01 – 3rd FLOOR SLAB CONCRETE WORKS (11.09.2020)

BLOCK 01 – 3rd FLOOR SLAB REINFORCEMENT WORKS (26.08.2020)

BLOCK 02 – 2nd FLOOR SLAB CONCRETE WORK (26.07.2020)

BLOCK 01 – 03rd FLOOR COLUMN REINFORCEMENT WORK & BLOCK 02 – 1ST FLOOR SLAB REINFORCEMENT WORK (23.06.2020)

CONCRETE WORK FOR 2nd FLOOR SLAB (03.06.2020)

SHUTTERING WORKS FOR 2nd FLOOR SLAB (30.05.2020)

CONCRETE WORKS FOR 2nd FLOOR COLUMN (29.04.2020)

BLOCK ONE 1st FLOOR COLUMN CONCRETE WORKS & BLOCK TWO 1st FLOOR COLUMN WORKS  (15.02.2020)

LEVEL TWO SCREED CONCRETE WORKS (15.01.2020)

1st FLOOR BEAM REINFORCEMENT FINAL WORKS (15.10.2019)

1st FLOOR BEAM REINFORCEMENT WORKS (01.10.2019)

GROUND FLOOR COLUMN SHUTTERING WORKS (01.09.2019)

BASEMENT-01 SLAB REINFORCEMENT FINAL WORKS (15.08.2019)

BASEMENT-01 SLAB REINFORCEMENT WORKS (31.07.2019)

BASEMENT-01 FORM WORKS (15.07.2019)

BASEMENT-01 COLUMN CONCRETE WORKS (01.07.2019)

BASEMENT-01 COLUMN REINFORCEMENT WORKS (30.05.2019)

BASEMENT-02 COLUMN REINFORCEMENT WORKS (15.05.2019)

BASEMENT-03 BEAM CONCRETE WORKS (01.05.2019)

BASEMENT-03 BEAM REINFORCEMENT WORKS (01.04.2019)

FOOTING, PLINTH BEAM, & LIFT WALL REINFORCEMENT WORKS (15.03.2019)

LAND EXCAVATION WORK (19.09.2018)

FOUNDATION STONE LAYING CEREMONY (10.04.2016)