SHUTTERING WORKS FOR 1ST FLOOR SLAB (15.07.2017)

1st floor column concrete works final stage (01.07.2017)

1st floor column concrete works (16.06.2017)

REINFORCEMENT WORKS FOR MEZZANINE FLOOR SLAB (01.06.2017)

 

FORM WORKS FOR 1ST FLOOR SLAB (15.05.2017)

CONCRETE WORKS FOR BASEMENT RAMP & 1st FLOOR COLUMN CONCRETE WORKS (30.04.2017)

 

CONCRETE WORKS FOR GROUND FLOOR SLAB (15.04.2017)

SHUTTERING & REINFORCEMENT WORKS FOR GROUND FLOOR SLAB (01.04.2017)

 

 

SHUTTERING WORKS FOR GROUND FLOOR COLUMN & SLAB (15.03.2017)

 

CONCRETE WORKS FOR BASEMENT SLAB (01.03.2017)

 

REINFORCEMENT WORKS FOR BASEMENT SLAB & SUMP (15.02.2017)

 

 

SCREED CONCRETE & BASEMENT SUMP PROVISION WORKS (31.01.2017)

SCREED CONCRETE & BASEMENT BEAM REINFORCEMENT (16.01.2017)

 

COLUMN REINFORCEMENT WORKS FOR GROUND FLOOR SLAB – 3rd STAGE (01.01.2017)

 

COLUMN REINFORCEMENT WORKS FOR GROUND FLOOR SLAB – 2ND STAGE (16.12.2016)

 

 

COLUMN REINFORCEMENT WORKS FOR GROUND FLOOR SLAB  (30.11.2016)

 

PILE CAP DEMOLISHING WORK – FINAL STAGE (17.11.2016)

 

 

PILE CAP DEMOLISHING WORK – 2ND STAGE (31.10.2016)

 

EXCAVATION WORKS & PILE CAP DEMOLISHING WORKS (19.10.2016)

SHORING WORKS (30.09.2016)

PILING WORKS  COMPLETED (15.09.2016)

 

PILING WORKS  – Final stage (31.08.2016)

 

PILING WORKS  – 2nd stage (16.08.2016)

PILING WORKS  – 1st stage (30.07.2016)

FOUNDATION STONE LAYING CEREMONY  (14.07.2016)

 

BHOOMI POOJA (13.07.2016)

 

PROJECT AREA (15.05.2016)

 

ALLOCATING THE PROJECT AREA (30.04.2016)

 

COMPLETION OF SOIL TESTING (18.04.2016)

 

SOIL TESTING (17.03.2016)

 

DEMOLISHING WORKS (16.02.2016)

 

PUNNIYASTHANA POOJAI (10.02.2016)